FINALIZE PROJECT PLAN & GAİN APPROVALS & GANTT CHART


DescriptionA project plan is finalized when it is formally accepted and approved by the project sponsor and other designated stakeholders. Formal approval acknowledges that all the deliverables produced during the Plan Stage are complete, reviewed and accepted.
Signatures on the project plan document indicate final approval. This sign-off marks the plan as the go-forward agreement and can be viewed as a project management milestone.
Rationale/PurposeThe project plan is important because it provides baseline information such as the budget, schedule and management plans for executing and controlling the project.   A signed project plan represents a commitment to continue and to dedicate the required time and resources toward the project.  It ushers the way into the Execute and Control Stage.
Who is InvolvedProject Manager
Project Sponsor
Project Stakeholders
ResultApproved Project Plan
Signed Project Plan Approval

Recommended actions and strategiesThe flow chart below describes the sequence of activities that results in a reviewed and approved plan.
1.
Compile deliverables or results from all the Planning Stage activities into a project plan document.
down arrow
2.
Distribute the project plan to the Project Sponsor and other appropriate stakeholders.
down arrow
3.
Schedule a meeting with Project Sponsor and other relevant stakeholders to review the project plan deliverables.
down arrow
4.
Make any changes from the formal review and finalize the project plan deliverable.
down arrow
5.
Ask the Project Sponsor to acknowledge if the project will proceed.
(This is a “go/no-go” decision point. The Project Sponsor should indicate the reasons for rejecting the project if the decision is a no-go.)
down arrow
6.
Obtain signatures from the Project Sponsor and any other designated stakeholder



Project Plan
 

Project Name:

Project Management Improvement Project

Example
Disclaimer
This example is based on a real project. However, this version is changed to present full examples of Project Plan components as described in the DoIT Project Management Framework. This example is not a true representation of the project plan for the Project Management Improvement project.

Project Plan Approval Signatures
 

Project Name:  Project Management Improvement


Project Manager

_______________________________________                   __________________  
                                (Signature)                                                                      (Date)
Name1 - Project Manager
DoIT Project Manager
Division of Information Technology – Systems Engineering and Operations                                         

Project Sponsor

_______________________________________                   __________________  
                                (Signature)                                                                      (Date)
Name2 - Project Sponsor
DoIT Process Manager
Division of Information Technology – CIO Office                                                         


Executive Sponsor

 _______________________________________                  __________________  
                                (Signature)                                                                      (Date)
Name3 - Executive Sponsor
Associate CIO
Division of Information Technology – CIO Office                                                         



Document Change Control
 

The following is the document control for revisions to this document.
Version Number
Date of Issue
Author(s)
V1.0
July 2005
Name1 - Project Manager
Approved version.










Definition
 

The following are definitions of terms, abbreviations and acronyms used in this document.

Term
Definition
CIO
Chief Information Officer
DoIT
Division of Information Technology



Table of Contents


1. Project Plan Overview and Critical Assumptions

The purpose of the Project Plan is to present the detail required to successfully execute and control the project, facilitate communication among project stakeholders, and document approved schedule baselines. The project plan is a living document and is expected to change over time as more information about the project becomes available.

The project plan was developed based upon certain key assumptions as noted in the Project Charter. Any changes to these assumptions may impact the project schedule, projected costs, the project scope and/or the project quality. These assumptions are:

·         The goals of this project support the vision, mission, and goals of DoIT, helping faculty, staff and students realize their visions through the use of information technology.
·         The project helps DoIT achieve its goal of outstanding customer service.
·         DoIT management actively supports improvements in each of the seven component areas: framework, tools, project management skills, thinking, culture, politics, and communication.
·         DoIT management and staff comply with specifications for all project management responsibilities as stated in the “Project Management at DoIT A Social Contract” document.
·         The timeline is reasonable and doable. The phased rollout supports early success and continued improvement.  The project includes a lengthy implementation as components are developed and implemented, followed by sustained competency and improvements in the seven component areas.
·         DoIT management assigns key project roles and adequate budget for the development and implementation of this project.
·         Effective, adequate, and appropriate levels of communication occur between DoIT management, the sponsor, and the project team during all phases of the project.
·         The framework deliverable avoids excessive detail to ensure common understanding, flexibility, and adoption.
·         The deliverables of the project are implemented DoIT-wide, supporting many diverse functional groups, projects, and customers.



2. Project Work Plans


The work breakdown structure identifies the project’s tasks to provide a framework for organizing and managing the work of the project.



















The purpose of the staffing plan is to make certain the project has sufficient staff with the right skills and experience to ensure a successful project completion.

Role Requirements
The following is a detailed breakdown of the roles required to execute the project. It includes: the project role, the project responsibility of the role, skills required, number of staff required to fulfill the role, the estimated start date and the expected duration the staff resource will be needed on the project.

Role
Project Responsibility
Skills Required
Number of Staff Required
Estimated Start Date
Duration Required
FY05-06
Project Team





Project Manager
Lead team, report status
Project Management
1
7/1/05
6 months
Core Team
Review deliverables, assure quality
Project Management
4
9/1/05
4 months
Content Developer
Create framework content
Research and web writing skills
1
9/1/05
4 months
Web Designer
Design web-based performance mgmt tool
Web design, web writing skills
1
10/1/05
3 months
Web Developer
Build the web-based performance management tool
Web development
1
11/1/05
2 months
Review Team
Evaluate deliverables, promote use
Project Management experience
20
11/1/05
2 months


Staff Assigned to Roles
The following is a detailed breakdown of the actual staff assigned to the project role, the amount of Full Time Equivalent (FTE) requested for the role, the actual FTE acquired, the labor rate and unit of the labor rate for the resource and the source from which the resource is recruited.

Role
Name
Requested
FTE
FY05-06
Acquired FTE
FY05-06
Rate
Rate Unit
Source
Project Team






Project Manager
Name1 - Project Manager
1.00
1.00
$85
hour
DoIT - Systems Engineering Operations
Core Team
Name4    
.10
.10
$70
hour
DoIT- Network Services

Name5
.10
.10
$70
hour
DoIT – Enterprise Internet Services

Name6
.10
.10
$70
hour
DoIT–Data Resource Management Technologies
Content Developer
Name6
.90
.90
$70
hour
DoIT–Data Resource Management Technologies
Web Designer
Name7
.05
.05
$75
hour
Academic Technology Solutions
Web Developer
tbd
.05
.00
$65
hour
Academic Technology Solutions
Review Team
(20 reviewers)
 Various Project Managers
.10
.10
$70
hour
See Appendix A for detail list
Total

   2.40
   2.35





Staff Resource Loading Chart
The following includes the estimated effort in Full Time Equivalent (FTE) days required by month for each staff resource assigned to the project.


FY05-06    FTE in Days
Role
Number of Staff Required
July
Aug
Sept
Oct
Nov
Dec
Total
Project Manager
1
15.00
15.00
15.00
15.00
15.00
15.00
  90.00
Core Team Members
4


4.50
4.50
4.50
4.50
  18.00
Content Developer
1


13.50
13.50
13.50
13.50
  54.00
Web Designer
1



3.50
1.50
1.50
   6.50
Web Developer
1




5.00
5.00
  10.00
Review Team
20




10.00
10.00
  20.00
Total

 15.00
15.00
 33.00
 36.50
  49.50
  49.50
 198.50


Training Needs
The following are the detailed training needs to bring staff to a level of skill required for project execution.

Role/Staff Resource
Training Need
Timeframe Needed
Anticipated Cost
Suggested Vendor/Method
Content Developer – Name6
Writing For Web
By  10/1/05
$2000
Vendor - Information Mapping

This section includes a Gantt chart and a project schedule for the project.

Gantt Chart

The Gantt chart graphically represents a project by showing each task as a horizontal bar whose length is the time needed to complete the task.


Project Management Improvement Project – Phase 1














2005






2006


June
July
August
Sept
Oct
Nov
Dec
Jan
1
Initiate Project








1.1
Develop Project Charter








2
Plan the Project








2.1
Develop Work Plan








2.2
Develop Project Control Plan








2.3
Finalize Project Plan and Gain Approvals








3
Execute and Control








3.1
Design Framework








3.2
Build the Framework








3.3
Test the Framework








3.4
Implement Framework








4
Close the Project









Project Schedule

The project schedule includes milestones, task dependencies, task duration, delivery dates, and staff resources assigned to complete the tasks.

Project Management Improvement Project – Phase 1
Effort Estimate in Days
Planned Start Date
Planned End Date
Resource
1
Initiate Project




1.1
Develop Project Charter




1.1.1
Define Scope
4.00
06/01/05
06/08/05
Name1 - Project Manager, Core Team
1.1.2
Define Requirements
3.00
06/09/05
06/15/05
Name1 - Project Manager, Core Team
1.1.3
Identify High-Level Roles
0.25
06/16/05
06/17/05
Name1 - Project Manager
1.1.4
Develop High-Level Budget
1.00
06/16/05
06/20/05
Name1 - Project Manager
1.1.5
Identify High-Level Control Strategies
0.50
06/21/05
06/21/05
Name1 - Project Manager
1.1.6
Finalize Charter and Gain Approvals
2.00
06/21/05
06/30/05
Name1 - Project Manager
1.1.6.1
Consolidate and Publish Project Charter
1.00
06/21/05
06/23/05
Name1 - Project Manager
1.1.6.2
Hold Review Meeting
0.50
06/24/05
06/24/05
Name1 - Project Manager
1.1.6.3
Revise Project charter
0.50
06/27/05
06/28/05
Name1 - Project Manager
1.1.6.4
Gain approvals
0.50
06/29/05
06/30/05
Name1 - Project Manager












2
Plan Project




2.1
Develop Work Plan




2.1.1
Develop Work Breakdown Structure
2.00
07/01/05
07/06/05
Name1 - Project Manager
2.1.2
Develop Project Staffing Plan
2.00
07/07/05
07/11/05
Name1 - Project Manager
2.1.3
Develop Project Schedule
3.00
07/12/05
07/14/05
Name1 - Project Manager
2.1.4
Develop Project Budget
3.00
07/15/05
07/20/05
Name1 - Project Manager
2.2
Develop Project Control Plan




2.2.1
Develop Communication Plan
1.50
07/15/05
07/17/05
Name1 - Project Manager
2.2.2
Develop Quality Management Plan
1.50
07/17/05
07/21/05
Name1 - Project Manager
2.3
Finalize Project Plan and Gain Approvals
5.00
07/22/05
07/29/05
Name1 - Project Manager
3
Execute and Control Project




3.1
Design Framework




3.1.1
Define framework stages and activities
5.00
08/01/05
08/15/05
Name1 - Project Manager, core team
3.1.2
Design framework content formats
1.00
08/16/05
08/18/05
Name7, Name6
3.1.3
Design web framework delivery tool
2.00
08/19/05
08/31/05
Name7
3.2
Build the Framework




3.2.1
Write the framework content
65.00
09/01/05
10/31/05
Name6
3.2.2
Review framework content for quality
12.00
09/15/05
10/21/05
Name1 - Project Manager, core team, review team
3.2.3
Build web tool prototype
20.00
08/19/05
08/31/05
Name7, web developer
3.3
Test the Framework




3.3.1
Test usability of web tool
4.00
09/19/05
11/25/05
core team, review team
3.3.2
Test usability of content
4.00
10/19/05
11/25/05
core team, review team
3.3.3
Adjust framework based on user feedback
5.00
11/18/05
11/30/05
Name6, Name7






3.4
Implement Framework




3.4.1
Move framework to production environment
5.00
12/01/05
12/16/05
Name1 - Project Manager
3.4.2
Announce availability of framework
0.50
12/19/05
12/30/05
Name1 - Project Manager
4
Close the Project




4.1
Conduct Post-Project Review
5.00
01/03/06
01/10/06
Name1 - Project Manager, core team, review team
4.2
Celebrate
0.50
01/13/05
01/13/05
Name1 - Project Manager, core team, review team




The project budget describes cost and budget needed to complete the project tasks.  It may include cost and budget for ongoing support after project completion.


Budget during the life of the Project

The budget below provides the detail estimates for labor, material and other items for the duration of the project.

Line Item
FY05-06
FY06-07


Labor
Material
Other
FY Total
Labor
Material
Other
FY Total
Phase I








1. Initiate Project








    1.1 Develop Project Charter
$8,600
$0

$8,600
$0
$0
$0
$0
2. Plan the Project








    2.1 Develop Work Plan








    2.2 Develop Project Control Plan
$15,000
$0

$15,000
2,000
$0
$0
$2,000
    2.3 Finalize Project Plan
$5,000
0

$5,000
$0
$0
$0
$0
3. Execute and Control Project








    3.1  Design Framework
$5,000
$0

$5,000




    3.2  Build Framework
$65,000
$0
$2000
$67,000
20,000
$0
$0
$20,000
    3.3 Test the Framework
$30,000
$0
$0
$30,000
10,000
$0
$0
$10,000
    3.4 Implement the Framework
$0
$0
$0
$0
$4,500
$0
$0
$4,500
4. Close the Project
$0
$0
$0
$0
$5,000
$0
$0
$5,000









Total
$128,600
  $0
$2,000
$130,600
$41,500
$0
$0
$41,500
Total Project Budget     $172,100

 
Comments: “Other”  is the budget estimate for a training class: Effective Writing for the Web


The on-going support budget is the detail estimates for on-going support after project completion.

Line Item
FY05-06
FY06-07
Total Budget
 Support Labor
$5,000
$5,000
$10,000
Total Two-Year Support Budget
$5,000
$5,000
$10,000

Comments: Support Labor includes an estimate for minimal support provided for case escalation from Help Desk assistance to users of the Project Management Advisor web site and an estimate for a staff resource to make small updates or corrections if problems are found.


3. Project Control Plans

Project Control Plans provide the basis to control and monitor the progress of the project.
The Project Control Plan includes the following detail plans that can be found in the Appendixes:

Defines the information needs of the project stakeholders and the project team by documenting what, when, where, and how information will be distributed.  See Appendix B.

Provides a plan that helps assure satisfactory project results by identifying project risks and factors that may cause each risk to be realized, specifying a process to follow during the Execute and Control Stage for detecting the occurrence of these factors, and specifying a process for responding to the resulting realized risks.  See Appendix C.
Appendix
 


Link to separate document.  (See example provided in PMA.)

Link to separate document.  (See example provided in PMA.)



1 yorum:

  1. If you are looking for a positive lending experience I would recommend Le_Meridian Funding Service. It is surprisingly easy to receive a debt help. You will be treated with respect and professionalism Because they helped me with loan too @ 1.9% ROI. They can fund project from $10,000 to $900,000,000,00 here is the company Email Contact..info@lemeridianfds.com
    WhatsApp...+19893943740

    YanıtlaSil